DECOMMISSIONING / DEMOLITION ADDITONAL SERVICES:

BODY SHOP OPERATIONS SPECIFICATIONS FOR:

•  Draining and flushing the weld water (supply and return) and compressed air services of Equipment and Tooling prior to removal.

•  Draining and flushing of the Weld Water System, prior to shutdown.

PAINT SYSTEMS AND EQUIPMENT SPECIFICATIONS AND DRAWINGS FOR:

•  Draining and flushing the Phosphate System (tanks and lines) prior to shutdown.

•  Draining and flushing the Elpo System (tanks and lines) prior to shutdown.

•  Draining and flushing the Paint (Prime, Color, and Clear) and Solvent lines prior to shutdown.

•  Draining and flushing the Sealer lines prior to shutdown.

•  Draining and cleaning the booth flood sheets, prior to shutdown.

•  Draining and cleaning the Sludge System, prior to shutdown

GENERAL ASSEMBLY (FINAL) OPERATIONS SPECIFICATIONS AND DRAWINGS FOR:

•  Draining and flushing the Gasoline, Diesel, Brake Fluid, Radiator, Power Steering, Transmission Fluid, Engine Oil, Front/Rear Axle Lubricant, Windshield Solvent, AC Refrigerant (R134A), Hydraulic Oil and Compressed Air Services of Equipment and Tooling, and the Facility Tank Farm, prior to removal.

•  Draining and flushing the Sealer lines prior to shutdown.

•  Draining and flushing the Glass (Primer and Urethane) lines prior to shutdown.

FACILITIES AND EQUIPMENT SPECIFICATIONS AND DRAWINGS FOR:

•  Draining and flushing of the Weld Water System, prior to shutdown.

•  Draining and flushing the Gasoline, Diesel, Brake Fluid, Radiator, Power Steering, Transmission Fluid, Engine Oil, Front/Rear Axle Lubricant, Windshield Solvent, AC Refrigerant (R134A), and Compressed Air Services of Equipment and Tooling, and the Facility Tank Farm, prior to removal.

•  Draining and cleaning the Sludge System, prior to shutdown.

•  Decommissioning Electrical Sub-Stations (Process and Building), prior to shutdown.

•  Decommissioning Electrical Buss (Process and Building), prior to shutdown.

•  Filling and covering Process and Facility Pits.

•  "Temporary" Handrail and Guarding around Pits, Trenches, Open Areas, and Abandoned Equipment.

•  The removal of overhead and floor supported Platforms, Mezzanines, Balconies, and Stairs.

•  Decommissioning Fire Protection, prior to shutdown.