GENERAL ASSEMBLY (FINAL) OPERATIONS SPECIFICATIONS AND DRAWINGS FOR:
Draining and flushing the Gasoline, Diesel, Brake Fluid, Radiator, Power Steering, Transmission Fluid, Engine Oil, Front/Rear Axle Lubricant, Windshield Solvent, AC Refrigerant (R134A), Hydraulic Oil and Compressed Air Services of Equipment and Tooling, and the Facility Tank Farm, prior to removal.
Draining and flushing the Sealer lines prior to shutdown.
Draining and flushing the Glass (Primer and Urethane) lines prior to shutdown.
FACILITIES AND EQUIPMENT SPECIFICATIONS AND DRAWINGS FOR:
Draining and flushing of the Weld Water System, prior to shutdown.
Draining and flushing the Gasoline, Diesel, Brake Fluid, Radiator, Power Steering, Transmission Fluid, Engine Oil, Front/Rear Axle Lubricant, Windshield Solvent, AC Refrigerant (R134A), and Compressed Air Services of Equipment and Tooling, and the Facility Tank Farm, prior to removal.
Draining and cleaning the Sludge System, prior to shutdown.
Decommissioning Electrical Sub-Stations (Process and Building), prior to shutdown.
Decommissioning Electrical Buss (Process and Building), prior to shutdown.
Filling and covering Process and Facility Pits.
"Temporary" Handrail and Guarding around Pits, Trenches, Open Areas, and Abandoned Equipment.
The removal of overhead and floor supported Platforms, Mezzanines, Balconies, and Stairs.
Decommissioning Fire Protection, prior to shutdown.
|